Rassvet: Russia's Answer to SpaceX's Kill Switch

In Kyiv on May 6, 2026, Oleksandr Komarov, chief executive of Kyivstar, signed an agreement making his company an authorized Starlink reseller for Ukrainian enterprises, schools, hospitals, and community clinics. He called it a “convenient and transparent channel.” VEON, Kyivstar’s Dubai-headquartered parent, did not announce exclusivity; consumer, government, and military procurement channels remain undisclosed. Behind him sit roughly 24 million mobile subscribers and a $1.16 billion 2025 revenue line, per Kyivstar’s FY2025 earnings. The agreement covers a real market segment. What it codifies for that segment matters even if it is not the only door. ...

May 10, 2026 · 8 min · DocB

811 Projects, 220 Gigawatts, One Bottleneck

The solar farm has permits, financing, a signed land lease, and grid-tie equipment sitting in a Pennsylvania warehouse. The developer cannot break ground. PJM Interconnection — the grid operator covering thirteen states from Chicago to the Atlantic — closed its queue in 2022 and only reopened it on April 29, 2026. The developer’s project is now one of 811 in the new cycle, behind hundreds of gigawatts of generation waiting for engineering studies under PJM’s reformed cluster process. ...

May 7, 2026 · 8 min · DocB

Hyperscalers Reserved $450B in Chips Nobody Can Plug In

The procurement schedule on the project manager’s screen has three columns that no longer line up. The high-bandwidth memory allocation, reserved with SK Hynix in early 2024, is firm for 2027 delivery. The transformer purchase order, placed later, has no committed date — the supplier is quoting roughly five years. The grid interconnection study queue, filed in parallel, stretches at least three years and often longer. ...

May 2, 2026 · 7 min · DocB

The Loudoun County Excavator That Moved the Yield Curve

The excavators were scheduled for Tuesday when the email arrived: your builder’s risk policy will not bind without catastrophe reinsurance, and the reinsurer just exited datacenter concentration risk. A construction project manager in Loudoun County, Virginia — the county that routes more internet traffic than any other on Earth — now sits with equipment idle, capital locked in escrow, and a hyperscaler contract that penalises delay. She cannot switch insurers because the market has contracted. She cannot redeploy the capital because it is committed. She absorbs the wait. The scene is drawn from developer accounts and insurance-market reporting; it represents a pattern now playing out across northern Virginia’s datacenter corridor. ...

April 18, 2026 · 8 min · DocB

33.5% Full: Inside Europe's Storage Gamble

The technician in Madrid’s Red Eléctrica control room now touches his screen every fifteen minutes, manually stabilising voltage across thousands of solar installations the grid was never designed to coordinate. Before the Iberian blackout, his job was passive monitoring — watching numbers drift within safe ranges, intervening perhaps twice per shift. Now it is active intervention — and every time an inverter cluster disconnects anyway, a gas turbine spins up to fill the gap. ...

April 8, 2026 · 7 min · DocB

2,600 Gigawatts Are Waiting. The Transformers Aren't Coming.

2,600 gigawatts are waiting. The transformers aren’t coming. A facilities engineer at a mid-tier cloud provider in central Texas has spent eleven months waiting for a grid interconnection agreement on a 150-megawatt data center expansion. The substation is visible from the parking lot. The fiber is lit. The servers are purchased. But the building sits half-empty because the local utility cannot schedule the transformer upgrade that would let the facility draw its full load. ...

March 30, 2026 · 8 min · DocB